Case between Antony Thomas vs K.P. Venugopal et al regarding rent arrears and subletting

Court
III ADDL. MUNSIFF & RENT CONTROLLER
Judge
SMT. REEJA R. NAIR
Order Date
2024-10-15
Duration
approximately-4 months 15 days

Judgement document from eCourt website

Open judgment PDF (eCourt)
Find Similar Cases

Case Summary

Antony Thomas, the petitioner, is seeking possession of a rental property due to non-payment of rent by the respondent K.P. Venugopal, who has also sublet the property without permission. The respondents did not appear in court, leading to an exparte hearing.

Judgment Outcome

Plaintiff Won
Interim Order
The court allowed the petition for rent arrears and ordered the respondents to deliver possession of the property to the petitioner within 30 days.
Judgment Favored
Plaintiff
Relief Granted
The respondents are directed to put the landlord/petitioner in possession of the petition schedule building within 30 days.
Case Type
Rent Control Petition
Final Judgment
No
Why Plaintiff Won:
The petitioner's claim of unpaid rent and unauthorized subletting was supported by uncontradicted evidence.

Judgment Evidence:

In the result: The petition is allowed u/s 11(2)(b) and 11(4) of the Act as follows: The respondents are directed to put the landlord/petitioner in possession of the petition schedule building within 30 days from today.

Parties Involved

Plaintiffs

Antony Thomas (68 years) Manayath House, Konthuruthy Road, Thevara P.O., Ernakulam, Kochi-13

Defendants

K.P. Venugopal (67 years) Chaniyamuriyil Malika Veedu, Punchiri Lane, Thevara P.O., Ernakulam-682013 Nandji Thakur (40 years) Sheebas Hair cutting Saloon, Thevara, Konthuruthy Road, Kochi-682013

Reliefs

Relief Type: Possession
Outcome: Granted
Description:
The respondents are directed to put the landlord/petitioner in possession of the petition schedule building.
Evidence:
The petition is allowed u/s 11(2)(b) and 11(4) of the Act as follows: The respondents are directed to put the landlord/petitioner in possession of the petition schedule building within 30 days from today.
Relief Type: Other
Outcome: Granted
Description:
The order passed under Section 11(2)(b) shall be subject to provisions under Section 11(2)(c) of the Act.
Evidence:
The order passed under Section 11(2)(b) shall be subject to provisions under Section 11(2)(c) of the Act.
Relief Type: Other
Outcome: Granted
Description:
The petitioner is entitled to realize costs of the suit from the respondents.
Evidence:
The petitioner is entitled to realize costs of the suit from the respondents.

Documents & Evidence

Document Type: Lawyer's Notice
Submitted By: Plaintiff
Relevance:
This notice was sent to the respondent regarding the rent arrears and subletting issue.
Reference:
Ext.A1
Document Type: Acknowledgment card
Submitted By: Plaintiff
Relevance:
This is an original acknowledgment card serving as evidence of receipt of the lawyer's notice.
Reference:
Ext.A2
Document Type: Acknowledgment card
Submitted By: Plaintiff
Relevance:
This is another original acknowledgment card serving as evidence.
Reference:
Ext.A3
Document Type: Photograph
Submitted By: Plaintiff
Relevance:
This photograph depicts the petition schedule building but was rejected due to lack of certification.
Reference:
Ext.A4

Quick Facts

Location
Ernakulam
Case Filed
Outcome Confidence
80%

Involved Entities

Private Individual

Similar Cases