Case Summary
The plaintiff, PEPCO, filed a suit against the defendant, P. P Corporation, for the realization of money. The suit was filed under the Code of Civil Procedure, claiming a sum of ₹201,891.
Judgment Outcome
Judgment Favored
Plaintiff
Relief Granted
The defendant shall pay ₹2,01,891/- with interest @ 12% per annum from the date of the suit till realization.
Case Type
Civil Suit
Final Judgment
No
Why Plaintiff Won:
The plaintiff successfully proved the claim for realization of money.
The plaintiff successfully proved the claim for realization of money.
Judgment Evidence:
a) The defendant shall pay ₹2,01,891/- (Rupees Two Lakhs One Thousand Eight Hundred and Ninety One only) with interest @ 12% per annum from the date of the suit till realization.
Parties Involved
Plaintiffs
Thomas Yacob (82 years)
Cherattumoolayil House, Kokkappilly Kara, Kokkappilly P O., Thiruvaniyoor Village, Kunnathunadu Taluk
Defendants
Ajith Kumar (52 years)
Mohanvilla, Vazhappilly West P O., Vazhappilly Village, Changanassery Thaluk, Annapoorneswary Road, Changanassery, PIN - - 686103
Reliefs
Relief Type:
Recovery
Outcome:
Granted
Description:
The defendant was ordered to pay ₹2,01,891/- with interest.
Evidence:
The defendant shall pay ₹2,01,891/- (Rupees Two Lakhs One Thousand Eight Hundred and Ninety One only) with interest @ 12% per annum from the date of the suit till realization.
Relief Type:
Costs
Outcome:
Refused
Description:
The plaintiff was not entitled to costs in the suit.
Evidence:
The plaintiff is not entitled to costs in the suit, considering the nature of the suit.
Documents & Evidence
Document Type:
Document
Submitted By:
Plaintiff
Relevance:
Documents from the plaintiff were marked and referred to during the hearing.
Reference:
Ext.A1 to A21